Good project handover notes let the next person start work without reconstructing the entire project. Begin with its current state and the next decisions due. Put historical detail behind links or clearly labelled references.

This template suits an internal transfer, holiday cover or a change of project owner. The amount of detail depends on how long the handover must last and how much context the recipient already has. A two-day cover note and a permanent transfer need different levels of explanation.

Copy this project handover template

Project and purpose:
Outgoing owner / incoming owner:
Handover date:
Current status, as of:
Next milestone and acceptance criteria:

Next three actions: action / owner / due date
Open decisions and who can approve them:
Known issues and possible risks:
Important contacts and their roles:
Working documents and where to find them:
Access required and how to request it:
Recent decisions that still constrain the work:
What is explicitly outside this handover:
Questions confirmed with the incoming owner:

The “as of” date matters. A note can be accurate when written and misleading a week later. Update it immediately before the handover, or identify which sections the incoming owner must verify.

A concrete handover example

Consider an illustrative office move. “The move is almost ready” does not tell the next owner what to do. A more useful opening is:

Office move, status as of 18 May. The moving company is booked for 30 May and the floor plan is approved. Internet installation is awaiting a confirmed appointment. The next owner needs to call the provider by 20 May, confirm building access with facilities and circulate the final desk plan after approval.

Follow that paragraph with the booking reference location, the facilities contact and the approved floor plan. Store credentials in the organisation’s approved password system; a handover should explain how to obtain access rather than contain passwords.

Separate issues, risks and assumptions

An issue needs attention now: a supplier has missed an agreed date. A risk describes an uncertain event: another delivery might be delayed. An assumption is something the plan currently treats as true, such as a room being available. Label them so the next owner knows whether to resolve, prepare or verify.

For each important item, include the effect on the project and the next step. “Supplier problem” is too vague. “Chair delivery delayed to 2 June; confirm temporary seating before the 30 May move” gives the recipient something to act on.

Check that the recipient can use it

  1. Ask the incoming owner to open the essential documents.
  2. Confirm the next three actions in their own words.
  3. Identify any missing approval or access.
  4. Agree who handles questions after the transfer.
  5. Record what they have accepted and what remains unresolved.

A link that works for you may not work for them. Checking access during the handover avoids an unnecessary delay later. Confirmation is also an opportunity to discover an unclear deadline before it becomes a missed commitment.

Keep working notes with the project

In Thoughts AI, you can write the handover as a note and organise it with the relevant project. Review the project’s contents and sharing settings before inviting a collaborator. Personal preparation and shared delivery notes may need different homes.

Link or reference the decisions that explain the current approach. Use a status update for ongoing reporting after the handover. The handover should give someone a starting point; the ongoing project notes keep that picture current.

Frequently asked questions

What is the most important part of a handover note?

Make the current state, next actions, responsible people and deadlines clear. The recipient also needs access to the documents and systems required to carry out those actions.

Can I use this template for holiday cover?

Yes. Specify the cover dates, decisions the temporary owner may make, escalation contacts and any work that should wait until you return.